Special Report | February 2014

Easing Iowa traffic congestion

The multi-lane roundabouts in NW 62nd Avenue in Johnston, Iowa, will help improve traffic flow, reduce delays, and promote pedestrian safety while presenting a smaller carbon footprint. PROJECTS INFO takes a look.  

DuPont Pioneer retained Foth Infrastructure & Environment LLC to secure funding for widening and reconstructing nearly 1.5 miles of NW 62nd Avenue in Johnston, Iowa, where the company's world headquarters is expanding. The initiative led to design and construction of a series of four multi-lane roundabouts the first in the state to address challenging traffic conditions.

 

Fast-track schedule drives design
 In early 2010, DuPont Pioneer announced to city and state officials that two campus expansions would create 638 new jobs, contributing to a significant increase in traffic on NW 62nd Avenue. Foth led a collaborative effort among the City of Johnston, the Johnston Economic Development Company, and DuPont Pioneer to complete two Revitalise Iowa's Sound Economy grants and secure $ 6.38 million in state funding for improving the corridor.

 

Given the existing traffic characteristics and imminent congestion, Foth saw an opportunity to implement a non-traditional intersection solution. Multi-lane roundabouts improve traffic flow, reduce delays, and promote pedestrian safety while presenting a smaller carbon footprint. Because this type of roundabout was new to Iowa, Foth was challenged to demonstrate the benefits to stakeholders. MicroStation was used extensively to prepare conceptual drawings and preliminary geometric layouts. These illustrations assisted with educating city staff, city councilmen, and key stakeholders about the benefits of the proposed solution.

 

Once approved, the project was put on a fast-track schedule, making it imperative for Foth's multi-discipline 12-member team to engage in collaborative design using optimal tools.

 

Interoperability produces master model
 GEOPAK Civil Engineering Suite offered a flexible suite of integrated tools for surveying and design of roads, sites, drainage networks, and storm and sanitary sewer systems. Foth maximised the benefits of GEOPAK in conjunction with other civil software to take on the challenging scope of work. In addition to multiple multi-lane roundabouts, the corridor featured a two-lane bridge, box-culvert underpass, recreational trail, and stream realignment.

 

GEOPAK site design tools were used to model the roundabouts, bridge berms, and stream realignment. GEOPAK's Corridor Modeler was used to model the roadway in between roundabouts, which involved the design of pavement widening and full reconstruction, as well as recreational trails. Foth used GEOPAK's data acquisition tools to import the models and create a 3D master model of the entire project. The master model was ultimately used to cut cross sections and serve as a reference during plan preparation.

 

In areas where the storm sewer network had to be retrofitted, GEOPAK drainage tools allowed the designers to lay out the existing network, then place additional nodes and pipes relative to the new alignment. This drainage model was exported into StormCAD for advanced network modeling, and then imported back into GEOPAK for final plan preparation.

 

Safety priorities
 Foth used FlowMaster and CulvertMaster to perform the extensive hydraulic analyses required for correction of Beaver Creek's course at the site where a two-lane bridge accommodated vehicular and pedestrian traffic. The channel was realigned, and the creek banks were reinforced to protect the new roadway embankment. The roadway was also raised above the creek's 100-year flood elevation to ensure it would be passable during seasonal flooding. GEOPAK's Roadway Designer generated the cross sections, which were imported into the U.S. Army Corps of Engineers Hydrologic Engineering Center's River Analysis System software. LEAP Bridge was used for the concrete bridge design. Pedestrian safety was another major design concern, since the project corridor passed through DuPont Pioneer's campus.

 

Each leg of each roundabout contained pedestrian ramps that were modeled in GEOPAK site design tools to ensure compliance with the Americans with Disabilities Act and public right of way accessibility guidelines. A 12-by-8 foot reinforced concrete box culvert was designed as an underpass allowing pedestrian traffic to cross safely under NW 62nd Avenue.

 

Plan preparation
 Laying out the roundabouts and pedestrian crossings required a staggering number of geometric and staking details. The design team devised an efficient process for detailing plan sheets using the 3D roadway design models. A Visual Basic routine automated the assignment of proposed elevations to coordinate geometry points. GEOPAK's Roadway Designer advanced plan preparation tools were used to automatically label the IDs of the points by selection sets, rather than individually. Once the ID labels were placed, GEOPAK automatically generated tables containing location information.

 

Design of the roundabouts was also influenced by the requirement to maintain two-way traffic flow during all stages of construction.

 

A fire station and 50 per cent of the community's schools are located on the east end of the project corridor, which is one of only two corridors connecting the city across Beaver Creek. Foth used alternate surfaces within GEOPAK's Corridor Modeler to piece together the construction stages. 

 

Customised inspection reporting
 

 

Foth developed a custom application that exported Bentley OnSite XML output to a central database. Inspectors had access to this data on rugged tablet PCs with survey-grade GPS capabilities, enabling the creation of real-time, as-built construction records. By extracting data from electronic diary entries and bid item inspections, Foth was able to automatically populate three unique inspection reports. One, the daily inspection report, contained several fields from the Bentley OnSite diary entry and had the capability to detect all bid items inspected during the same day. These bid items were pulled by name, along with quantity and location information, to populate a final report. Upon project delivery, the as-built data was converted into GIS format for the owner's use in long-term maintenance.

 

Returns on innovation
 Innovations in plan preparation shaved a total of 24 days from the project schedule, according to Foth's estimates. The design team streamlined the process by merging the 3D models built in various GEOPAK modules to create one 3D master model. With the master model to use as a reference during plan preparation, this methodology saved an estimated 120 hours valued at $ 13,200 and cut 14 days from the project schedule.

 

Plan sheet detailing took up to 60 per cent less time, thanks to the automated workflow used to detail more than 1,000 geometric and staking callouts on the plan sheets. When final design revisions were made, it took minutes to update the plan sheets rather than the hours spent identifying which points had changed and updating them individually. Foth estimated that automating this process saved about 90 hours of manual drafting valued at $ 9,000 and cut 10 days from the project schedule. It also reduced errors on the final plan sheets and, subsequently, during construction stakeout.

 

When the bidding time was shortened to 10 days, Foth was able to create a solid plan set and released electronic data to all contractors and subcontractors. Bentley software was used to create data in various file formats requested by contractors, including non-native formats such as DWG, XML, and TTM. The availability of electronic plan sets reduced the risk to contractors and made their bids more competitive. Of the eight bids submitted, six were within 3.7 percent of each other. Coming in 20 percent below the engineer's estimate, the low bid of $ 7 million was just 0.2 percent lower than the next lowest bid.

 

Finally, Foth's innovative approach to onsite inspection reporting saved an estimated 10 hours per week valued at $ 57,200 over the 52 week construction contract.

 

Based on Bentley OnSite, the automated reporting process replaced handwritten diary entries, manual as-built measurements and calculations, and manual data entry on final inspection reports. Now all diaries and quantities are stored in a database, adding value for the owner after project completion. Transportation studies suggest that the multiple, multi-lane roundabouts will result in a 90 per cent reduction in traffic fatalities, 76 percent reduction in injuries, and 35 percent reduction in crashes. In addition to improved safety, the design will save $1,500 per day in travel time value and an estimated $3,600 per day in fuel consumption.

 

Project summary:
 Organisation:
Foth Infrastructure & Environment, LLC
 Solution: Roads
 Location: Johnston, Iowa

 

Project objective:
 Widen and reconstruct nearly 1.5 miles of NW 62nd Avenue in Johnston, Iowa, to manage travel demand through 2032.

 

Secure two Revitalise Iowa's Sound Economy grants totaling $6.38 million in state funding. Design and construct a series of four multi-lane roundabouts to improve safety, increase travel speeds, and reduce travel time and fuel consumption.

 